Client Handoff Plan

Status: Team plan updated October 26, 2026. Client-controlled destination accounts, workstation access, CAD versions, final appointment, and acceptance criteria remain unconfirmed.

Handoff outcome

Adcut should finish the semester with a working local application, source and release materials it controls, repeatable installation and recovery instructions, operator and developer documentation, test evidence, and a clear list of limitations. A GitHub link by itself is not a complete handoff.

Delivery package

ItemDelivery methodVerification
Application releaseSigned or checksummed Windows package if feasible; locked uv source installation as the documented fallbackFresh Windows machine starts and processes a permitted sample
Source and historyClient-controlled GitHub repository or transferred archive with release tagClient can clone/download without a student account
DocumentationUser manual, install/update guide, architecture, test report, known limitationsAll links open from a client-controlled location
TrainingLive walkthrough plus captioned install/start and convert/export videosClient representative repeats the core workflow
Test assets and evidencePermitted samples, expected results, CI logs, CAD/import recordsEvidence is versioned and reproducible
Ownership recordWritten account, license, dependency, cost, and credential inventoryNo required asset remains solely under a student account

Step-by-step handoff

  1. Confirm the client owner, target Windows workstation, supported AutoCAD/IGEMS versions, repository destination, and final handoff appointment.
  2. Freeze the accepted requirements and identify features or tests that remain incomplete.
  3. Create a release candidate from a reviewed commit and rerun the full automated matrix.
  4. Test installation, start, conversion, SVG/DXF download, restart, update, and uninstall on a clean Windows machine.
  5. Run client-approved CAD import and physical validation; record results without marking unavailable tests as passed.
  6. Copy or transfer code, releases, samples, documentation, videos, and issue history to client-controlled storage.
  7. Conduct a walkthrough: install, process a sample, interpret warnings, verify scale and paths, report a defect, recover from failure, and obtain updates.
  8. Have the client representative repeat the workflow and record accepted items, rejected items, deferred work, and owners.
  9. Verify access after the meeting and provide the final release identifier and checksums.

Accounts, ownership, cost, and dependencies

Acceptance checklist

Contingencies

If standalone packaging is not stable, deliver the locked uv installation with a tested startup script and explain the additional dependency. If CAD or cutting access is unavailable, deliver automated and visual evidence while labeling production validation as blocked. If repository transfer cannot be completed, provide a verified archive and written instructions, but keep transfer as an open action.